How much will bringing utilities to the land cost me? Well, the short answer is that it depends. Utility costs can be anywhere from $10,000 to over $30,000 depending on your location and proximity to public utility connections. Furthermore, some cities and power companies charge more for their services.
Rates for extending water and sewer lines can run $50 to $100 or more per foot. With a long run of, say 200 feet, fees can reach to $20,000 or more! Power companies tend to charge less, but cost could still reach several thousand dollars for similar run, including the cost of a transformer.
To get started, you basically have two choices: temporary power from a portable generator or temporary power from the local utility pole. In most cases, the goal will be to have stable, permanent power from a utility company once your project is complete.
There are several common methods to consider to get water to your land when public water is unavailable, such as drilling a well, using a holding tank, or even utilizing a nearby stream. Perhaps the most dependable way to get water to your land is by drilling a well.
It costs about $3 million per mile to convert underground electric distribution lines from overhead, while the cost to build a mile of new overhead line is less than a third of that, at approximately $800,000 per mile, according to a section on PG&E’s website called Facts About Undergrounding Power Lines.
Connecting electricity
Each provider will charge a different amount to connect electricity, but on average it will cost between $12-90, depending on who you sign up with.
Water Main Installation Cost
House service water main installation costs $1,577 on average with most paying between $613 and $2,572. You’ll spend anywhere from $50 to $250 per linear foot, depending on length, material, depth and accessibility. You’ll need a city permit which varies in price from location to location.
Below Is A Table Of Each Individual Service And Average Prices.
Process | Average Price Range | Extras |
---|---|---|
Equipment* | $160-$230+ | If Heavy duty equipment is required you run the risk of having to pay a rental fee between $60-$150 per hour |
Land Survey | $500.00 | |
Permits | $30-$200 + | |
Excavation | $1,300-$4,500 |
Public water is commonly provided by a governmental entity or water company. To find out whether public water is available, look at the details of the sales listing for the land or talk to the seller or a real estate agent (if one is involved).
Most of the time, a telephone pole that has to be replaced because of an accident can cost anywhere from $3,000 to as much as $6,500 for the pole and installation.
…
How much does a telephone pole cost?
Pole Size | Price Range |
---|---|
45-foot | $400 to $700 |
50-foot | $500 to $850 |
55-foot | $650 to $850 |
Call a water divination expert or practice the technique yourself. Water divination is also known as dowsing and utilizes two L-shaped or Y-shaped rods or twigs to detect water below ground. Hold one rod in each hand stretched in front of you, and slowly walk over the property.
Water for most rural homes come from either a spring or a well. Some homes may use water from a river, pond or lake, however this is typically only done when a well or spring is not available. Water from a spring or a well is considered “ground water.” “Surface water” comes from sources such as lakes or rivers.
Wells are the most obvious answer, but there are several other ways to source water sustainably.
Contact your utility company and provide them with the details of your installation, such as your home’s distance from the road, the amperage you need and the location of your property.
A new 138 kV overhead line costs approximately $390,000 per mile as opposed to $2 million per mile for underground (without the terminals).”
As an example, for a 120-volt circuit, you can run up to 50 feet of 14 AWG cable without exceeding 3 percent voltage drop.
…
For 240-volt circuits:
14 AWG | 100 feet |
---|---|
12 AWG | 120 feet |
10 AWG | 128 feet |
8 AWG | 152 feet |
6 AWG | 188 feet |
In most cases, it can cost anywhere from $10,000-$30,000 to hook up to nearby utilities. Again, the cost will be dependent on your location and proximity to utility connections. Always budget for more than the estimated costs because costs always wind up running over.
To arrange a new electricity connection for your self build home or for a temporary supply while you build, you need to contact a ‘Distribution Network Operator’ (DNO) for the connection and an ‘energy supplier’ to arrange a meter.
Cost to Wire a House per Square Foot
House Size | Average Cost (Installed) |
---|---|
1,600 sq.ft. | $4,800 – $8,000 |
2,000 sq.ft. | $6,000 – $10,000 |
2,500 sq.ft. | $7,500 – $12,500 |
3,000 sq.ft. | $9,000 – $15,000 |
The average cost to get utilities on land is $20,000. It costs an average of $2,650 to hook up to a municipal water system. You can expect to pay an average of $3,000 to set up electrical work, $1,650 to survey the land before connecting utilities.
How to Set Up Utilities
The Raw Land Development Process: How To Develop Land In 6 Steps
Agricultural Land Values Highlights
The United States farm real estate value, a measurement of the value of all land and buildings on farms, averaged $3,160 per acre for 2020, no change from 2019. The United States cropland value averaged $4,100 per acre, no change from the previous year.
Undeveloped land is truly a tabula rasa. When you have virgin dirt, you can do essentially anything you want that meets your community’s zoning restrictions and your budget. … Undeveloped land has no utilities, intra-parcel roads or pre-defined building site, so you’ll have a lot of work to do get ready to build.
Landowners typically have the right to use the water as long as such use does not harm upstream or downstream neighbors. In the event the water is a non-navigable waterway, the landowner generally owns the land beneath the water to the exact center of the waterway.
Some water underlies the Earth’s surface almost everywhere, beneath hills, mountains, plains, and deserts. … The ground above the water table (the pink area) may be wet to a certain degree, but it does not stay saturated.
GPR can detect a wide range of buried utilities including gas, electrical, telecommunications, and water. The radar signal can detect materials commonly used for utilities such as various types of pipe, conduit, wiring, and fiber optic.
A distribution transformer can take one hour to a few hours to replace; but widespread damage can take much longer to repair.
When a transformer blows, it interrupts electrical service to any residences or businesses connected to the transformer. Electric service crews must replace the destroyed hardware, first shutting down the incoming electrical line to prevent damage and injury.
How much does it cost to install a power meter? Installation or replacement of an electric meter box is $250 to $700. You have to pay $40-$120 for the labor cost per hour and they can take 2-4 hours. Homeowners often replace a panel and meter together.
Temporary power must have a pole within 70 feet or less to the worksite and the necessary permits to supply electricity. Depending on the project, the cost of temporary power can vary.
…
Temporary Power for Construction Site Cost.